Here’s The Scoop…The Hits Just Keep On Coming…Pavilion Permits….. Better Late Than Never?…

PAVILION PERMITS….AFTER THE FACT…HMMM…BETTER LATE THAN NEVER…./IT’S GOOD TO BE THE GOVERNMENT…DIFFERENT RULES APPLY?…

This writer heard something was amiss…with the pavilion…but what more could there be…after missing walls…uninstalled plumbing hook-ups…surely there could not be more?…

Or could there?…

THE PAVILION BEGAN….WEEKS AGO….THE PERMIT WAS APPLIED FOR ON…..ON 12/1/08…
1. https://dpep.broward.org/bcs/default.asp?PossePresentationId=1210000&PosseObjectId=22191160

Permit Application

Permit Number:         08-02627

Master Permit Type:         BLDG: ACCESSORY BUILDING

Create On Final:         Certificate of Completion

Building Use:         Commercial

Parcel Information

Folio Number:         9318-01-2270

Address:         4501 OCEAN DR – PAVILION

LAUDERDALE BY THE SEA FL 33308

Jurisdiction:         Lauderdale by the Sea

Legal Description:         LAUDERDALE BY THE SEA 6-2 BLOT 1 BLK 24

Parcel Owner Information

Name:         TOWN OF LAUDERDALE BY THE SEA

Mailing Address:         4501 N OCEAN DR

LAUD BY THE SEA FL 33308-3610

Permit Information

Present Use:         PAVILLION

Proposed Use:         PAVILLION

Job Value:         $303,648.00

Square Footage:

Occupancy Type:

Type Of Construction:

Occupant Load:

Minimum Finish Floor Elevation:

Must be the higher of                 feet above road crown

OR                 feet above mean sea level

Application Date:         12/01/2008

Expiration Date:

Permit Holder

General Contractor:         MC GEDDY, GARY JOSEPH

License Number:
CB C053647 – BUILDIN State of Flori

Owner Builder
…………………………………………………………………………………………………………………………………..

THE INSPECTION ….. 12/12/08…..

The electrical passed…The plumbing passed…The structural…REJECTED…OOPS!….

(NOA-example)…..http://www.miamidade.gov/buildingcode/library/productcontrol/noa/07041109.pdf.

http://www.miamidade.gov/buildingcode/pc-search_app.asp

……………………………………………………………………………………………………………………………………….
2. https://dpep.broward.org/bcs/default.asp?PossePresentationId=1460000&PosseObjectId=22197087

Plan Review

Permit Number:         08-02627         Reference Number:         22191160

Status:         Waiting for Customer

Comments:         PAVILION

Reviews

Type

Status

Date Completed

Plan Reviewer

Comments

Electrical         Approved         12/12/2008         Marjorie Jocosing

Fire         Not Applicable

Mechanical         Not Applicable

Plumbing         Approved         12/12/2008         Marjorie Jocosing

Structural         Rejected         12/12/2008         Jennifer Lofton         View Comments

THE COMMENTS….FOR FAILED STRUCTURAL….

Structural Review Notes
Note Type     Note Text
Building General Comments     08-02627
4501 N Ocean Blvd
Pavilion

FBC 106.3 Minimum standards for plan submission;

Include on the plans the building data:

Type VB Construction
Group A-5 Occupancy

Address the NOA’s for the Hardi-Plank siding.

Address the Trellis by submitting the shop drawings now or explain.

Submit the NOA’s for the truss anchors in duplicate reviewed and approved by the design professional of record per FBC 2321.7.

Address the Bike rack details or explain.

Provide a building application for the roof membrane system.

Shall be accompanied by duplicate HVHZ Uniform Permit Application completed with submittals as stated in the application

………………………………………………………………………………………………………………………………………………………………………….

Some questions…
The Manager said we have no walls…despite this writer seeing renderings with walls …up until….12/12/08….(day of the inspection)…being delivered to Town Hall from the contractor…why would the contractor need to ” Address the NOA’s for the Hardi-Plank siding.”…if no walls were being  built?…

The Manager said there will be no bathrooms and no plumbing was done for future bathrooms…despite the bids including bathrooms…why the plumbing inspection…. that passed?

The Manager said the cost awarded to Coastal Construction for this job was $370,810.00…why does the permit state…” Job Value…… $303,648.00″?…..

Seems like all those who came before the Commission to receive a “slap” for any delay/or questionable intent with their permits……need  a “second bite of the apple”?…

No double standards should apply…..

more to come…..