PAVILION BIDS….
change of venue…just a few in attendance so it took place in the Town Hall Conference room….
5 Bids received…..
In Attendance…….
Assistant to the Manager John Olinzock
This writer
Reps from….Tenex/MBR/SA Consultants
IN THE ORDER THEY WERE OPENED…by the Town Clerk…June White….
1. Coastal Contracting…..$370,810.00
2. Sanalil Construction…..$749,947.00
3. SA Consultants………….$539,910.00
4. Tenex……………………….$646,456.50
5. MBR Construction……….$477,010.00
HOW THIS PROCEEDS….
Per …..Assistant to the Town Manager….John Olinzock….
The Town Architect will review over the next 2 days….
Check out the Bid-Bonds….
The Town Attorney will review for legal corporations…etc….
Put in front of the Commission…July 8, 2008….
Note:…..the amount designated for this project was $900,000.00…..
Do not know if the Broward Commission has extended our grant…..approx..$156,000.00
more to come….